STEVESTON HIGHWAY MULTI-USE PATHWAY PROJECT PHASES 1 AND 2 – UPDATE
这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。
Option 1 is to amend the budget for the Steveston Multi Use Pathway, Phases 1 and 2 capital
projects to address the budget shortfall of $2.49 million. The budget increase encompasses all
tendered and estimated costs provided through a competitive procurement process. Staff have
engaged with TransLink to seek additional funding for this project, however, TransLink has advised
additional cost sharing for this project is not available. Award of construction contract for Phase 1
and Phase 2 of this project would proceed immediately following Council approval of the budget
increase. Ongoing consultation will occur during the construction phase of the project through
notification to all impacted stakeholders and abutting property owners prior to commencement of
construction activity and ongoing communication to address any comments or questions raised
regarding the construction process. The additional funding required to cover the anticipated costs
for the project are available in the Roads DCC ($2,341,845) uncommitted balance and Capital
Reserve-Revolving Fund ($149,400). Should Council endorse this option, the Consolidated 5 Year
Financial Plan (2023-2027) will be amended accordingly.
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开官方 PDF ↗版本与字符定位
留存文件 SHA-256:aaaaee4bb4d47172c7dd0d3854a93e17f4bef060b1f56c4c1d72fcca678e0d78
文本 SHA-256:8b1788b32a60bba790c11534156a6c80fe5b4cb2f799d7740c5a145473142ceb
抽取:pymupdf-1.26.7-native-footer-ocr150-eng-7d4322bd2a774972-v1
第 16–16 页;字符 33332–34549(末端不含)