R26/14-6 It was moved and seconded
That a Heritage Alteration Permit be issued to authorize deconstruction and reconstruction of the First Nations Building at Britannia Shipyards National Historic Site, as outlined in the report titled “Heritage Alteration Permit Application (HA 26-011972) by the City of Richmond – 5180 Westwater Drive (First Nations Building)”, dated June 22, 2026, from the Deputy Chief Administrative Officer and General Manager, Parks, Recreation and Culture.
The question on Resolution No. R 26 /14-6 was not called as in reply to queries from Council, staff advised that (i) the design plans have been discussed with the First Nations Building Committee (FNBC), Britannia Shipyards National Historic Site Society (BSNHSS) and Musqueam First Nation with support from most groups, (ii) two heritage consultants and an archeologist have been inside the building and both groups have provided reports that will be brought back to the FNBC for review, (iii) the Indigenous Relations Manager will be touring the site but their role on the project is limited because of the FNBC and approved Terms of Reference, and (iv) during the concept design phase, staff have reached out to a moving company.
As a result of the discussion, the following referral motion was introduced:
R26/14-7 It was moved and seconded
That the Heritage Alteration Permit be referred back to staff to have an archeologist review the building prior to deconstruction, include the City’s Indigenous Relations Manager and other First Nation groups on the project, and to contact Supreme House Movers Ltd. to request a report on moving the building.
The question on Resolution No. R26/14-7 was called and it was DEFEATED with Mayor Brodie, Cllrs. Day, Hobbs, Loo and McNulty opposed.
Further discussion ensued with respect to (i) staff to look at options on lifting and moving the building, (ii) how the City can maintain the history and purpose of the building, (iii) the deconstruction process is detailed and any new learnings will be taken into account in the future interpretation of the building, and (iv) the importance of moving forward with the project to avoid losing the $3.4 million grant from the Province of BC's Growing Communities Fund that expires in 2028.
The question on Resolution No. R26/14-6 was then called and it was CARRIED with Cllr. Wolfe opposed.
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开原始来源 ↗版本与字符定位
留存文件 SHA-256:0ef9426404180cf130cd3a28fd68374494f285ca54b04286769027ab5dd3d8b0
文本 SHA-256:fed5b7259361f697bacb5f48971f8bdd768ec0e02cfd513662afef576612a742
抽取:richmond-minutes-dom-blocks-v1
字符 21633–23995(末端不含)