Staff Report to Council
Application No.: 7922-0118-00
Planning & Development Report
Page 5
The EV fast charging stations will be located on the east side of the site, adjacent to existing
parking stalls. An additional stall will be located on the west side of the property to account
for the conversion of regular parking stalls to stalls for EV charging. The proposed site plan
will convert 2 parking stalls to EV charging stations and add one parking stall. In total, there
will be 4 regular stalls, 1 handicap stall, and 2 EV charging stalls for a total of 7 stalls.
Sustainability Considerations
The proposed development will provide alternative fuel infrastructure on an existing lot.
POLICY & BY-LAW CONSIDERATIONS
Zoning By-law
Setback Variances
The applicant is requesting the following variances:
o to reduce the minimum flanking side yard setback of the CD Zone from 12 metres to
0.37 metres for Accessory Buildings and Structures to allow for the construction of
electric vehicle charging stations and accompanying infrastructure;
o to reduce the front yard setback of the CD Zone from 12 metres to 3.34 metres for
Accessory Buildings and Structures to allow for the construction of electric vehicle
charging stations and accompanying infrastructure;
Part 7 of the Zoning Bylaw, Special Building Setbacks, states that setbacks on a lot abutting an
existing or future highway as shown on the "Surrey Major Road Allowance Map", attached as
Schedule K to the Surrey Subdivision and Development Bylaw, are to be calculated from the
ultimate property line. According to the Surrey Major Road Allowance Map, a 2.0 metre
Special Setback along 152 street is required. The total minimum setback along 152 Street will
be 2.37 metres to the EV charging station infrastructure, and 0.37 metres from the ultimate
property line.
The proposed setback variances will allow for the construction of EV charging stations on
site. This meets OCP policy direction to expand energy efficient transportation infrastructure
and encourage building and site upgrades that accommodate EV charging stations.
The proposed site plan will convert 2 stalls to EV charging stations and add one parking stall
to allow the site to meet the minimum required parking requirements. In total, there will be
4 regular stalls, 1 handicap stall, and 2 EV charging stalls for a total of 7 stalls.
Staff support the requested variances to proceed for consideration.
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开官方 PDF ↗版本与字符定位
留存文件 SHA-256:6e39c083bf7e0a9d47da6462210624ac62bb787585fce6e83309312a8ccf7a36
文本 SHA-256:7ee418b5fe672ad64ff0cd4d9796a2c284432ac1d5e83f02ecce081c3cdd81ce
抽取:pymupdf-1.26.7-text-pages-v1
第 5–5 页;字符 5869–8391(末端不含)