The proposed 3-year TUP will be valid from the date of approval. A TUP can be extended only
once for a further maximum 3-year period subject to Council approval. The applicant is aware
of this timeline and has indicated that their plan is to redevelop the property in accordance
with the Anniedale-Tynehead NCP (see Appendix III for Future Development Concept).
•
The applicant has provided a site plan for the proposed truck parking and outdoor storage use
that includes the following:
o parking spaces for approximately 25 oversized trucks and trailers are proposed within
northwest corner of the site;
o outdoor storge of metal and rebar is proposed in the centre of the site;
o the existing 11-metre wide drive aisle located along the south property line is proposed
to be retained to provide access to the site from 177A Street;
o the existing vacant school building located at the southwest corner of the site is
proposed to be used as office space and washroom facilities for the proposed
temporary use; and
o landscape screening and fencing is proposed to complement existing trees around the
perimeter of the site.
•
Vehicular access will be from 177A Street in the southeast corner of the site. As noted above,
the applicant is required to complete required road pavement widening and upgrades along
177A Street, 97 Avenue, 179 Street, 96 Avenue, and 180 Street to provide truck access
(8.0 metres pavement) from the site through to Golden Ears Way at 180 Street (approximately
740 metres of road works).
•
The subject site has existing intermittent tree buffers along the north (Highway 1) and west
(Highway 15) sides, which the applicant proposes to supplement with additional tree and
shrub planting and fencing to screen the use from these major roads.
•
The applicant is proposing to erect an 8 ft. tall black chain link fence with privacy screens
along the south lot line to screen the use from existing residential properties to the south.
•
The applicant has committed to continue to work with staff on the proposed landscaping and
fencing details to ensure appropriate buffering as a condition of TUP issuance (should Council
support the proposed temporary use). The landscaping and fencing will be required to be
installed and inspected prior to TUP issuance and securities would be collected to ensure the
landscaping and fencing is maintained over the course of the TUP.
•
The proposed temporary truck parking and outdoor storage use will allow for the interim use
of the land until it is economically viable for redevelopment.
•
The proposed temporary truck parking and outdoor storage use will assist in providing much-
needed authorized truck parking spaces and outdoor storage space in the City.
Referrals
Engineering:
The Engineering Department has no objection to the project
subject to the completion of Engineering servicing requirements as
outlined in Appendix II.
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开官方 PDF ↗版本与字符定位
留存文件 SHA-256:9328ae53f2f926989b02a3f49bdff24f1fd45a42b3869b1f7c5c6e4d688ce604
文本 SHA-256:bf154a89f3cbacd29ad4bd2a0637c383b02b14d6b59b7f7db35500dea9f0b912
抽取:pymupdf-1.26.7-text-pages-v1
第 5–5 页;字符 6768–9844(末端不含)