Public Electric Vehicle Charging Network – Direct Current Fast Charging Expansion
这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。
BC Hydro will not confirm electrical capacity until a formal application is
submitted, staff have selected sites where high voltage lines are available and close to the
proposed locations of the chargers. These projects involve connecting to a dedicated 1.5 MW
commercial-level pad-mounted transfonner, which is a more complex and a higher-demand
installation than a typical residential service upgrade. Should BC Hydro dete1mine that an
upgrade is not feasible at any site, one of the potential future sites would be selected for similar
review and potential installation.