NORTH DIKE UPGRADES CONCEPT PLAN - LYNAS LANE TO NO. 2 ROAD
这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。
- 7 -
Financial Impact
This project is included in the Government of Canada's Disaster Mitigation and Adaptation Fund
grant award, which provides the City with $13. 7 8M for the upgrade of drainage pump stations
and perimeter dike upgrade projects, including this section along the North Dike between Lynas
Lane and No. 2 Road. The grant funding is based on Federal funding up to 40% of eligible costs,
up to a total project value of $34.45 million. Funding to complete the design and construction of
this project has been approved by Council as part of the Capital Budget through the Disaster
Mitigation and Adaptation Fund Infrastructure Upgrades projects in 2020, 2021, 2022, 2023, and
2024.
Conclusion
Guided by the City's Flood Protection Management Strategy, Dike Master Plan Phase 2 and as
approved through the Capital Budget, staff have advanced the preliminary design for the North
Dike along River Road between Lynas Lane and No. 2 Road. The current concept plan is
presented to inform Council of the project status and to seek Council's approval to proceed with
public engagement.
Kevin Roberts, P.Eng
Senior Project Manager
Engineering Design and Construction
604-204-8512
7672407
Braeden LeBlanc, EIT
Project Manager
Engineering Design and Construction
604-204-8928
PWT - 19
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开官方 PDF ↗版本与字符定位
留存文件 SHA-256:33c333da20cb1cbd45e6dac86754a7b3e99e4412bd98f698da8ec8114f91a68d
文本 SHA-256:3d420aad4cea56e2b646aab97e9d9073f4b0e5eeff81d4d7063b4c7314fd8b57
抽取:pymupdf-1.26.7-text-pages-v1
第 7–7 页;字符 9952–11264(末端不含)