Arterial Roadway Improvement Program (2021), Top 20 Collision Prone Intersections - Implementation of Medium/Long-term Improvements (2021), and Top 20 Collision Prone Intersections - Implementation of Medium/Long-term Improvements (2022) – Project Update
这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。
Increasing project budgets as outlined in Option 1 will allow all projects except the
Alderbridge Way and No. 4 Road intersection to be completed as planned. Detailed design of all
projects is underway