steveston cannery channel dredging project update and expanded scope of work

这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。

As these areas have never been formally dredged and lack historical data, they fall outside of the ongoing maintenance-based permitting process requiring additional analysis and cost estimates, and follow standard, longer duration project permitting approval timelines. To support this work, staff recommend including this dredging work as Phase 4 through an extension to the existing Phase 2 and 3 contracts. This would enable work to commence immediately following completion of Phase 2 and 3 in February 2027.