PROPOSED AMENDMENT TO THE DEVELOPMENT COST CHARGES IMPOSITION BYLAW
这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。
The proposed increase of DCC recoverable value from $1.22 billion (2017) to $1.87 billion
(2023) was mainly the reflection of the following cost drivers:
•
Building Construction Price Index for Metro Vancouver (as published by Statistics
Canada) has increased by over 40% since 2017 which was attributed to the rising costs of
labour, raw materials and commodities that have been exacerbated by the pandemic and
global supply chain issues. The increase has specifically affected the projected costs of
the Engineering programs where raw materials and associated construction costs are
significant cost drivers in providing the required capital infrastructures.
•
Increase in land values over the past years, especially notable in the densified City Centre
area where land value has increased by more than two-folds. Both the Roads and the Park
Acquisition DCC program values have been updated to reflect the current land
acquisition costs for the roadways and park spaces required by growth.
•
A new diking component has been included in the proposed Drainage DCC program for
the City to provide a robust dike network and infrastructure with increased capacity to
support growth.
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开官方 PDF ↗版本与字符定位
留存文件 SHA-256:72cf362fd7196a3f5b38fd4593c53640438c4388fa1a668e2a7f453bbd10206c
文本 SHA-256:4fcea7e023ec4cc2f23db7ee08cafe5ad5c7068c3a3f6b115a3503d87e2ae21d
抽取:pymupdf-1.26.7-text-pages-v1
第 5–5 页;字符 8127–9323(末端不含)