CAMBIE ROAD AND NO. 5 ROAD INTERSECTION UPGRADE, NO. 2 ROAD MULTI-USE PATHWAY AND ACTIVE TRANSPORTATION IMPROVEMENT PROGRAM 2022 – PROJECT UPDATE
这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。
$749,750
$767,066
Funding Secured
Amended Project
$3,450,000
$3,149,750
$1,517,066
Budget
Contractor pricing has been received for the Cambie Road and No. 5 Road Intersection Upgrade
Project and No. 2 Road Multi-Use Pathway Project. Should Council approve the budget increase
recommended in this report, staff will proceed with awarding the construction contracts for these
projects. The Cambie Road and No. 5 Road project would be scheduled for completion by the
end of 2024, and the No. 2 Road project by early 2025.
The Active Transportation Improvements Program is planned to be constructed by City Forces.
Should Council approve the recommended budget increase, this project would be scheduled for
completion by early 2025.
Conclusion
The Cambie Road and No. 5 Road project improves safety and relieves traffic congestion for
road users. The No. 2 Road Multi-Use Pathway and the Active Transportation Improvement
Program 2022 improves comfo1i, safety and connectivity for those who walk, cycle or roll within
the City. These projects improve the City's transportation network and were approved by
Council as part of prior Capital Budgets.
7618994
PWT - 29
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开官方 PDF ↗版本与字符定位
留存文件 SHA-256:5f8f9126b663b86a9909d5b29a990e6e2fae9da1c6217f4c3864c0a2b6e5b769
文本 SHA-256:73afc3956b5c581baf0de594f38f45788eba3212e66f3970faba5f3a1f29fa4c
抽取:pymupdf-1.26.7-text-pages-v1
第 5–5 页;字符 10083–11267(末端不含)