CAMBIE ROAD AND NO. 5 ROAD INTERSECTION UPGRADE, NO. 2 ROAD MULTI-USE PATHWAY AND ACTIVE TRANSPORTATION IMPROVEMENT PROGRAM 2022 – PROJECT UPDATE
这段原文取自本站留存的同一份 PDF,仅展示本条相关文本;官方在线版本可能更新。
April 24, 2024
- 5 -
Pedestrian lighting would not be provided along this MUP and the deteriorated surface
would not be repaired.
The additional external funds secured, in addition to the previously approved budget amounts,
provide sufficient funding to complete these projects. Amending the budgets to fully utilize the
secured grants will allow the projects to be completed as intended with no impact to City
funding. Staff recommend that project budgets be increased to reflect the additional grants
secured.
If project budgets are not increased to utilize the secured grants, there would be insufficient
funding to complete the projects. The projects would not proceed and roadways will be left in
their current conditions. Any external funding secured for these projects would be lost.
Financial Impact
Staff recommend that an increase to the capital projects' budgets, funded by external
contributions with no additional City funding required, in the amounts as outlined in Table 2 be
approved, and that the Consolidated 5 Year Financial Plan (2024-2028) be amended accordingly.
Table 2: Financial Impact Summary
Active
Cambia Road and
Transportation
No. 5 Road
No. 2 Road Multi-
Improvements
Intersection
Use Pathway
Program 2022
Project
Upgrade (CR00101)
(CT00034)
(CR00138)
Approved Budget
$2,760,000
$2,400,000
$750,000
Additional External
$690,000
非商业公共资料研究与事实报道;仅展示核对事实所需的已评估摘录及本站中文说明。版权归原作者或发布机构;不表示来源机构认可本站。原文、来源及使用条款见链接。 来源使用条款 ↗
打开官方 PDF ↗版本与字符定位
留存文件 SHA-256:5f8f9126b663b86a9909d5b29a990e6e2fae9da1c6217f4c3864c0a2b6e5b769
文本 SHA-256:73afc3956b5c581baf0de594f38f45788eba3212e66f3970faba5f3a1f29fa4c
抽取:pymupdf-1.26.7-text-pages-v1
第 5–5 页;字符 8690–10083(末端不含)